Shorncliffe Station is a heritage-listed terminus on Queensland’s Shorncliffe line. The station closed in November 2025 for a major renewal and accessibility upgrade.
The project restored the original footprint of the 1914 station building. It also provided raised boarding points, accessible ramps and toilets, new lighting, CCTV, customer information systems and other passenger facilities.
Degnan Constructions was the Design and Construct contractor for Queensland Rail. Degnan engaged Waterline as its specialist low-voltage electrical engineering partner.
Heritage rail projects have complex design and construction interfaces.
At Shorncliffe Station, the project team had to upgrade the electrical systems while it protected the heritage features of the site. The team also temporarily moved the historic station building onto temporary footings during construction.
The principal challenges included:
The electrical design had to support the construction sequence without causing delays to the project.
Waterline reviewed and updated the existing Queensland Rail electrical design. Waterline then prepared the complete Issued for Construction package.
The design covered:
Waterline also supplied:
The Waterline team included:
Waterline coordinated the electrical design with Degnan, Queensland Rail and the other project consultants. This work helped the project team identify and resolve design interfaces before construction.
Waterline delivered the electrical design to the project program. This supported the completion of the upgrade and the return of Shorncliffe Station to public service on 27 July 2026.
The project delivered:
The new lighting improves safety, visibility and the passenger experience while it respects the heritage setting.
Discover how Waterline’s solutions can bring precision and expertise to your engineering projects.